Bombay High Court questions TISS's Rs. 141 crore compensation estimate and orders a fresh assessment of fishermen's livelihood losses within six months.

The Bombay High Court has rejected a proposed Rs. 141 crore compensation package for fishermen affected by Thane Creek Bridge III and ordered a fresh assessment of their livelihood losses.
The Tata Institute of Social Sciences (TISS), which was appointed to assess the impact of bridge construction on local fishing communities, had recommended the amount. The court found that its calculations lacked sufficient supporting income records and scientific evidence.
In their October 16, 2026 judgment, Justices Bharati Dangre and Manjusha Deshpande acknowledged that construction had affected fishing activities. They directed a task force to examine the losses and determine compensation within six months.
TISS submitted its compensation assessment in November 2025, following directions from the High Court.
The TISS report estimated direct livelihood losses of approximately Rs. 94 crore for 2021-22 to 2024-25. It also proposed livelihood security support for subsequent years, bringing its overall compensation estimate to around Rs. 141 crore.
The court questioned the calculation because much of it relied on income losses reported by the fishermen themselves. It said these figures needed to be checked against official records before compensation could be determined.
The court also questioned the use of assessment methods drawn from other coastal projects, including the Mumbai Trans Harbour Link. Unlike those projects, Thane Creek Bridge III was built alongside existing bridges without major coastal reclamation, making a direct comparison difficult.
The court also examined the proposed Rs. 141 crore compensation against the bridge's reported construction cost of approximately Rs. 500 crore.
Fishing societies representing communities from Vashi, Juhu, Koparkhairane, Ghansoli and Diva approached the High Court seeking compensation for the impact of the bridge project.
The petitioners said construction work had affected their traditional fishing grounds and reduced their access to parts of the creek.
Thane Creek Bridge III provides additional road connectivity between Mumbai and Navi Mumbai. It has been constructed to improve the capacity of this heavily used road. The bridge is part of wider efforts to improve connectivity across the Mumbai Metropolitan Region, alongside other major road infrastructure projects in Mumbai.
During the hearing, a report carried out by the Central Marine Fisheries Research Institute (CMFRI) was taken into consideration. This report looked at the impact of the construction on the local fisheries and environment.
The study found that fishing continued in parts of the creek during construction, although areas occupied by the bridge pillars could no longer be used for fishing.
It was acknowledged by the court that there has been some impact on fisheries. However it was unclear how much of a financial impact this had on individual families.
The court has now left the compensation calculation to a task force, which will examine the claims afresh.
The task force will determine the number of affected fishermen, their fishing activity and loss of income due to the construction.
The Task Force shall consider data from the Fisheries Department, technical analysis and other relevant data. It shall also consult with the Maharashtra State Road Development Corporation (MSRDC) which executed the bridge construction and Navi Mumbai Municipal Corporation.
While considering the previous reports from TISS and CMFRI, the Task Force shall independently arrive at conclusions.
Compensation will be calculated in accordance with the Maharashtra government's applicable policy, based on the losses established during the reassessment. The task force has six months from the October 16 judgment to complete its work. The final amount payable to the affected fishermen is yet to be decided.