Maharashtra orders work to stop on Adani Green's 1,500 MW Tarali project over pending NBWL clearance, while scrutiny continues over disputed project cost figures.

The Maharashtra Forest Department has ordered work to stop at Adani Green Energy's 1,500 MW Tarali Pumped Storage Project in Satara district, citing the absence of prior approval from the National Board for Wildlife (NBWL).
The notice, issued on November 13, 2026, concerns the project in Patan taluka. The company has been asked to explain why work began without wildlife clearance and submit the required documents within three days of receiving the notice.
The project is also under scrutiny over its cost figures. While its estimated cost was earlier recorded at Rs. 5,675 crore, an affidavit submitted in September 2026 cited Rs. 56.75 crore. Adani Green has denied reducing the overall project cost, saying the smaller amount referred only to survey and investigation expenses.
The notice was issued by the Satara Forest Division asking the project authorities to halt work until they obtain appropriate permissions.
The department has requested a detailed response along with statutory clearances, project maps and tree-felling permissions. The department has also asked the project authorities to provide details on the number of trees that have been approved to be cut down.
Failure to comply with this may result in action being taken under relevant forest and wildlife laws.
The Tarali project will be developed in the Tarali dam reservoir area and covers an area of around 150.74 hectares within Nivade, Tondoshi, Kalambe and Jalu villages in Patan taluka.
According to the Forest Department, the project falls within the deemed eco-sensitive zone of the Koyna Wildlife Sanctuary, which forms part of the Sahyadri Tiger Reserve. Adani Green disputes this position, maintaining that the project is outside notified protected areas and the reserve's buffer zone.
The difference in the project's reported cost has raised questions about the amount payable towards wildlife conservation.
The environmental clearance issued in February 2025 recorded the project's estimated cost at Rs. 5,675 crore. The State Board for Wildlife had stipulated a contribution of 4% of the project cost towards conservation activities linked to the Sahyadri Tiger Reserve.
Originally, according to the project estimates, the contribution would be Rs. 227 crore. But, in September 2026, the cost of the project was mentioned in an affidavit as Rs. 56.75 crore. And the State Wildlife authorities agreed to consider this amount which reduced the contribution to about Rs. 2.27 crore. The company was initially asked to pay Rs 56.75 lakh and the remaining amount after NBWL approvals. However, the initial amount was paid.
Rohan Bhate, Honorary Wildlife Warden of Satara district took objection to the revised calculation and filed a complaint. The Union Environment Ministry directed on November 6 to the state forest department to probe the matter urgently.
Adani Green denied any attempt to reduce their statutory obligations by reducing the project cost.
“The allegation that the company sought to revise project costs downwards to diminish statutory obligations is completely misleading,” a company spokesperson said.
The company maintained that Rs. 56.75 crore referred to survey and investigation expenses, while the overall project estimate remained Rs. 5,675 crore.
In a statement issued on November 16, Adani Green maintained that construction had commenced after obtaining the requisite approvals from the concerned authorities.
According to the company, it received a certificate confirming that no forest land was involved on January 23, 2024. Environmental clearance was granted on February 11, 2025, followed by Consent to Establish from the Maharashtra Pollution Control Board on April 7, 2025.
The company also maintained that the project does not involve any notified protected area or forest land and is located outside the notified buffer zone of the Sahyadri Tiger Reserve.
On wildlife clearance, Adani Green said it had submitted a proposal to the NBWL after receiving a recommendation from the State Board for Wildlife. The proposal is still under consideration.
The Forest Department's notice, however, concerns the absence of prior NBWL approval when work began. The stop-work order does not cancel the project, but construction remains subject to the department's direction and the required wildlife clearance.