A decade after RERA's launch, India has recorded 1.6 lakh project registrations, but delayed refunds and weak enforcement remain key challenges for homebuyers.

The Real Estate (Regulation and Development) Act was first notified on 1 May 2016, when 61 of its 92 sections came into effect. The remaining provisions including the core framework for project registration, buyer protection and dispute resolution took effect on 1 May 2017. And so the RERA completed 10 years of its initial commencement on 1 May 2026
A lot has changed since. Projects must now be registered, Buyer money has to be kept in escrow, Approvals are public, separate forums to take complaints to and so many other regulations came into effect. All to make homebuying more transparent than it has ever been.
RERA did not arrive all at once. It was rolled out in two phases, a year apart, and each one added a key part of the framework. Lets start from the start
| Date | Milestone |
| 10 March 2016 | Rajya Sabha passes the RERA Bill |
| 15 March 2016 | Lok Sabha passes the RERA Bill |
| 25 March 2016 | President gives assent to the Act |
| 1 May 2016 | RERA partially comes into force; 61 of 92 sections notified |
| 1 May 2017 | RERA comes into full force; all remaining sections take effect |
| 1 May 2026 | RERA completes 10 years since initial commencement and 9 years as a fully operational law |
Before RERA, Indian homebuyers often had to decide with very little information. Project approvals, construction progress, fund use and delivery dates were largely in the developer’s hands. Buyer money could be moved from one project to another. Marketing claims were hard to check. And when a project was delayed, the buyer had few practical options.
Take a simple example. A family pays a booking amount for a flat based on a brochure and a verbal promise of possession in two years. They have no easy way to see if the project is approved, where their money is going or what the builder is legally bound to deliver. If the date slips, they can only keep calling the sales office.
RERA was introduced to correct this imbalance. Its mandate is to regulate and promote the real estate sector, ensure transparency in the sale of plots, apartments and buildings, protect homebuyers and enable faster dispute resolution. In effect, it sought to move Indian real estate from developer discretion to documented accountability.
| Area | Before RERA | After RERA |
| Project information | Limited public disclosure | Mandatory registration and project-level disclosures |
| Buyer funds | Funds could be diverted across projects | 70% of collections must be deposited in a separate project account |
| Marketing | Claims were difficult to verify | Advertisements and bookings require registration; violations can attract penalties up to 10% of estimated project cost |
| Disputes | Fragmented consumer and civil remedies | Dedicated RERA adjudication mechanism with a 60-day disposal target |
| Buyer confidence | Information asymmetry favoured developers | Buyers can check project status, approvals and complaints on state RERA portals |
RERA at 10 in numbers
RERA completed 10 years since initial commencement on 1 May 2026 and nine years as a fully operational law on 1 May 2017.
Cumulative project registrations crossed 1.6 lakh nationwide by May 2026.
Around 1.6 lakh cases have been disposed of over the past decade.
More than 1 lakh complaints have been resolved through formal channels.
Indian real estate attracted a record $30.7 billion in equity inflows between 2024 and Q1 2026, up 88% from the preceding two-year period.
The numbers show clear progress. But they also reveal the scale of the challenge: a market selling close to 3 lakh homes annually in the primary segment cannot rely on a dispute system that resolves cases slowly or leaves orders difficult to execute.
RERA’s biggest unfinished business is enforcement. While project registration and disclosure have improved, the experience of buyers seeking refunds, compensation or possession after a favourable order remains uneven.
For instance, Pune district illustrates the gap between an order and actual relief. As of September 2026, 176 MahaRERA recovery cases worth ₹106.72 crore remained pending despite orders in buyers’ favour. Across the wider recovery exercise, 475 cases worth ₹332.53 crore were taken up, of which 180 cases worth ₹119.08 crore were settled through mutual agreements and 16 cases worth ₹9.53 crore were recovered through property auctions.
The pending cases reflect practical hurdles: recovery warrants had been issued in 133 cases worth ₹87.01 crore, while 82 cases worth ₹86.02 crore were caught in litigation. In some matters, properties could not be traced; in others, auctions failed to produce adequate recovery.
Moreover, several northeastern states and Ladakh also lacked permanent RERA authorities as of June 2026, exposing gaps in nationwide implementation. Maharashtra’s decision to appoint dedicated recovery officers for MahaRERA cases is a positive step, but consistent execution across states will decide whether orders translate into refunds.
RERA’s first decade created the right to relief. Its next phase must ensure the delivery of relief.
What the next decade needs
RERA’s next phase must move from documentation to delivery. The priority should be:
Uniform, time-bound enforcement of RERA orders across states.
Stronger and faster recovery mechanisms for refunds and compensation.
Permanent RERA authorities in all remaining states and union territories.
Real-time digital tracking of construction progress, escrow utilisation and complaint status.
Greater accountability for project extensions and delayed delivery.
Better coordination between RERA, consumer commissions, courts and local approval bodies.
RERA built the architecture of trust in Indian real estate. Its first decade made buyers ask better questions, developers disclose more and regulators act as a visible interface between the two.
Its next phase must prove that trust is not merely documented bit it is enforceable. For India’s housing market to deepen further, RERA must ensure that a buyer’s victory is not just an order on file, but a home delivered or money returned.