The Chennai Metropolitan Development Authority (CMDA) To Introduce Deemed NOCs for High-Rise Buildings
The Chennai Metropolitan Development Authority (CMDA) is set to transform the approval process for high-rise buildings (HRBs) by introducing deemed No Objection Certificates (NOCs). This groundbreaking initiative aims to expedite the approval process for buildings exceeding five floors or 18 meters in height, promising significant improvements in the efficiency of the construction and real estate sectors.
Streamlining the Approval Process
In May 2022, the CMDA introduced an online plan permission system, which currently approves an average of 70 plans monthly, including over 70 high-rise buildings annually. This is a notable increase from the pre-digital era, where the figures were significantly lower at 35 and 60, respectively. Despite these advancements, the approval process has traditionally been slow, taking at least 45 days primarily due to the need for multiple NOCs from various stakeholder departments.
In the Chennai Metropolitan Area, the process of obtaining No Objection Certificates (NOCs) for both high-rise and non-high-rise buildings, as well as layout and subdivision approvals, involves 21 departments, including state and Union government agencies. While most departments are integrated with the Chennai Metropolitan Development Authority’s (CMDA) online portal, developers of high-rise buildings need specific approvals from several key agencies:
- Tamil Nadu Fire and Rescue Services (TNFRS): Approval is required to ensure fire safety standards are met.
- Airports Authority of India: Necessary for buildings that are 30.5 meters high or above ten floors.
- Chennai Metro Rail Limited (CMRL): Required if the building is within the metro alignment.
- Water Resources Department (WRD): Mandatory if the building is near water bodies.
- Public Works Department (PWD): A structural stability report must be obtained.
- Environmental Clearance: Required for projects measuring 20,000 square meters or more.
New NOC Timelines
Under the proposed system, the CMDA has suggested a 30-day timeframe for issuing NOCs. The first seven days will be allocated for inspection and document scrutiny by the relevant department. Following this, applicants must submit the required documents within two weeks. Finally, within the subsequent ten days, the NOC must be issued, or it will be deemed granted if the department fails to provide it on time. The issued NOC will be reflected in the plan permission portal, ensuring transparency and accountability. Additionally, random inspections will be conducted to ensure compliance.
Implications for the Industry
Industry leaders have praised this initiative as a major breakthrough. S Sridharan, Vice-President of CREDAI National, South, remarked that if implemented effectively, this could significantly accelerate the housing and construction industry. Homebuyers stand to benefit from quicker project deliveries, and the streamlined process is expected to attract substantial investments from other states to Tamil Nadu.
A Mohamed Ali, President of Credai Chennai, echoed these sentiments, highlighting that timely approvals would help meet the growing demand for housing. The proposed changes are anticipated to enhance the overall efficiency of the construction process, reduce bottlenecks, and foster a more favorable environment for developers and investors.
Broader Context and Future Outlook
This development is part of a broader trend toward digital transformation in the construction and real estate sectors. By leveraging technology, regulatory bodies like the CMDA aim to reduce administrative delays, enhance transparency, and improve service delivery. The introduction of deemed NOCs is a critical step in this direction, reflecting the CMDA’s commitment to fostering a more dynamic and responsive regulatory environment.
Additionally, this initiative aligns with the state’s broader goals of promoting urban development and addressing the housing needs of a rapidly growing population. As urban areas continue to expand, efficient regulatory frameworks will play a pivotal role in ensuring sustainable and balanced growth.
Conclusion
The CMDA’s introduction of deemed NOCs for high-rise buildings marks a significant milestone in the evolution of the approval process in Chennai’s construction industry. By setting clear timelines and integrating key departments into a cohesive digital platform, the CMDA is poised to enhance efficiency, attract investment, and meet the housing demands of the future. As this initiative unfolds, it is expected to set a benchmark for other regions to follow, driving progress and innovation in urban development across India.